Your block · 4 min read

Building on the Peninsula: bushfire ratings, overlays, soil and septic tanks

Peninsula blocks come with conditions that a suburban block in Melbourne often does not. None of them are unusual, and all of them are cheaper to design around at the start than to discover once the drawings are approved.

Checked against official sources 23 November 2026

An excavator beside the original house with holes open in the ground where the footings are being dug

Why the block matters as much as the house

Two identical houses can cost very different amounts to build on two different blocks. Between Mordialloc and Portsea, the things that make the difference are fairly predictable: bushfire ratings, planning overlays, flood prone land, the soil, the wind and salt off the water, and on the older back-beach blocks, whatever was buried before the sewer arrived.

Every one of the items below has turned up on a job we have built. Find out which apply to your block before you design, and they are just part of the brief.

What to check, and what it means

  1. Bushfire prone areas and BAL ratings

    Large parts of the Peninsula are designated bushfire prone areas. New homes in those areas must be built to at least BAL-12.5 (Bushfire Attack Level), and higher ratings apply closer to bushland. The rating sets requirements on external walls, windows, decking, screens, roofs and even the gaps around doors, well before anyone chooses a finish. Additions can carry requirements too; your building surveyor will confirm what applies. Three of our recent Peninsula jobs were BAL 12.5.

  2. Planning overlays

    Your planning property report lists any overlays on your land. On the Peninsula the common ones deal with bushfire, vegetation, landscape, heritage and flooding. Overlays can mean you need a planning permit for work that would not need one elsewhere, including removing trees. Check before you design, not after.

  3. Flood prone land

    If your block is on designated flood prone land, the council has to be reported to and give its consent before a building permit can be issued, and floor levels may be set for you. We built a carport at Mount Eliza on a block that was both BAL 12.5 and flood prone. Both just had to be part of the plan from the start.

  4. Soil class and footings

    Soil is classified by how much it moves with moisture, and that classification decides how the footings are designed. Get a soil report early. Without one, an engineer may design to an assumed class and leave it to the builder to confirm the ground on site, which is exactly how footings end up deeper than the drawings show. At one Blairgowrie job, some piers went down 2.7 metres before they found ground worth building on.

  5. Wind and salt

    Every site gets a wind classification that affects how the frame and roof are tied down, and exposed coastal sites rate higher. Salt air is hard on anything metal. On coastal jobs we use hot dip galvanised steel for exposed fixings and treated timber rated for weather. It does not change how a build looks. It changes how long it lasts.

  6. Septic systems, old and current

    Parts of the Peninsula are still unsewered, and much of it was on septic long before the sewer arrived. If your home is on septic, adding bedrooms or plumbing can mean altering the system, which needs a permit from the Mornington Peninsula Shire. Systems are sized on the number of bedrooms plus one, and the Shire asks you to allow up to 42 working days for a permit. Even on sewer, old tanks are often still in the ground: we have found them under two separate Blairgowrie houses, both where footings had to go.

How to find out before you design

  • Download your free planning property report from VicPlan: zone, overlays and bushfire prone area status.
  • Get a copy of your title and plan of subdivision for easements and covenants.
  • Ask the council whether your property is on designated flood prone land.
  • Commission a soil report before the engineer designs the footings.
  • If you are on septic, ask the Shire for the existing system’s permit records.
  • Ask neighbours and long-time locals what turned up when they built. On the back beaches, that is often the best record there is.

How we handle it

Most of our work is on the Peninsula and Bayside, so we look for these things at the first site visit rather than after the drawings are approved. Where something cannot be known until we dig, it goes into the estimate as an allowance, and if something turns up, it is priced and put in writing before we dig any further.

Official sources

General information, not legal or financial advice. Rules change, so check the sources above for the current position before you sign anything.