Carrum Downs
Two bedrooms and a rumpus, added to the back of a Carrum Downs house
A 55 m² Nuline weatherboard addition on the back of a brick veneer home: two new bedrooms with robes, and a rumpus room with built-in storage. Practically complete about three months after we started on site.
- Type
- Rear addition
- New floor area
- 55 m²
- Rooms
- Two bedrooms, rumpus, storage
- Cladding
- James Hardie Nuline weatherboards
- Build time
- About 3 months
- Suburb
- Carrum Downs
- Completed
- November 2026
More house, without starting again
The house is a single-storey brick veneer home with a tiled hip roof. The extra room goes on the back: Bedrooms 3 and 4, each with a robe, and a rumpus room with a wall of storage behind bifold doors. It opens straight off the existing hallway, so the front of the house stays as it was.
Weatherboard and a low skillion, on purpose
Matching existing brick is a losing game, so the addition does not try. It is clad in James Hardie Nuline weatherboards instead, on a timber-framed addition sitting on stumps, with the boards running down past the floor line to the ground so there is no exposed subfloor. Weatherboard is lighter and quicker to put up than brick, it does not wait on a bricklayer, and the finished addition reads as a deliberate new wing rather than a near-miss on the old brick. The roof is Colorbond Kliplok at a two-degree pitch, falling away to the back of the block, and the drawings have the whole existing tiled roof resprayed to blend with the new Colorbond, so old and new read as one house from the street.
Practically complete in three months
From the day we started on site to practical completion took about three months. Lightweight framing and Nuline cladding helped: once the frame was up and the roof was on, the addition was closed in and the trades could work inside regardless of the weather.
The paperwork behind 55 square metres
A small addition still needs a full set of documents before anyone digs a stump hole: a soil report, structural engineering, a performance solution for the energy rating, and consent to build over an easement. Then four mandatory inspections - stump holes, subfloor, frame and final. The building permit was issued on 1 July 2026 and the certificate of final inspection on 5 November 2026.
In their words
“Josh, Nathanael and entire team did an amazing job on our extension. They were involved all the same from design stage and delivered an exceptional extension. The attention to detail was there for the entire build. Could not recommend them any higher.”
Inside the extension
Outside